MONITORING > Madaniyat-Djalal-Abad (km 507 to km 574) Rehabilitation of 67 km, Section Madaniyat-Djalal-Abad CAREC Corridor 3 (Bishkek-Osh Road) Improvement Project, Rehabilitation of 67 km of Bishkek-Osh Corridor, Section Madaniyat-Djalal-Abad (km 507 to km 574) № | Earth Works | Unit | Scope per design | Actually completed
| % of completion |
1
|
Clearing and grubbing
|
ha
|
0
|
0
| |
2
| Cutting and grubbing of trees |
pcs
|
12 000
|
12 000
|
100%
|
3
|
Excavation and disposal of suitable material from existing road to reuse as fill material |
m3
|
390 000
|
20 822.27
|
5,3%
|
4
|
Formation of embankment using common soil from borrow pits
|
m3
|
354 000
|
20 822.27
|
5,9%
|
5
|
Excavation and dispose of unsuitable soil to a spoil area
|
m3
|
32 000
|
23 301.12
|
72%
|
№ | Drainage Works | Unit | Scope per design | Actually completed | % of completion |
1
|
Pipe culverts, d= 1.0 m
|
pcs
|
1800
|
9
|
1%
|
Data as per June 2020 report
|